Barrel First-Flush Diverter — step-by-step guide

The principle

Multi-barrier, not single-point. Sediment, then biology, then storage on a level plinth so water always flows where you want it. Food-grade containers only — never a tank that once held chemicals.

Materials

  • 2-4 large reclaimed barrels (200L)
  • first-flush ball valve
  • hose/piping
  • overflow to swale

Tools

  • Spade
  • level
  • drill
  • spanner
  • hose cutter

Reclaimed from

Stockyards + food-industry recyclers + OLX barril + farm suppliers